Location: Carrara Queensland
Contract Value: $1 million
Construction Period: 6 Months
Type Of Contract: Construct Only
Client: Gold Coast Water

Nerang/Broadbeach Road Water Main Upgrade project involved excavation, pipe laying and backfilling of 2km 600mm & 750mm DICL pipe. Traffic control on this job was a challenge as we had 1 lane closed on Nerang Broadbeach rd the entire length of the project.

Being a Mains Road controlled road restoration was a high priority as was safety having police onsite during night works.

Live connections to existing mains were completed under strict shut down time frames without incident.

International Certifications FSC Accreditation | ISO 9001 | AS/NZS 4801 | ISO 14001