Location: Gold Coast Queensland
Contract Value: $5 million
Construction Period: 6 Months
Type Of Contract: Construct Only
Client: Queensland Government

Molendinar Reservoir project involved excavation, pipe laying and backfilling of 800m of 1200mm Sintakote pipe. The pipeline included in ground and aboveground, construction with the CC Pipe and Civil specialised concrete construction team building structures to support the 1200mm main as well as building valve pits with thrust restraints. Connections to the existing reservoir pipe work was also a challenge working with shut downs under strict time limits. Pipe installation involved rubber ring joints as well as collar welded joints at bends, Air valve Tees and Scour Valve tees. Restoration of the alignment involved road repair and seeding.

Nerang River Crossing Tunnel Bore (Abigroup)

Nerang River Crossing project involved the loading of a 1500mm tunnel bored sleeve under the Nerang River and associated connection pipe work. The challenge for this project was the depth of the shafts approx 23m deep and the bore being designed with long radius curve requiring every pipe had to be installed to match redius and welded into place.  The connection pipe work was laid vertically inside the shaft to a tee and air valve and welded to the existing pipe work on both sides of the river. Restoration of the alignment involved road repair, laying turf, seeding and restored and treated ASS dewatering ponds from the tunnelling operations.

International Certifications FSC Accreditation | ISO 9001 | AS/NZS 4801 | ISO 14001